NEW QUESTION 42
What do you need to setup in order to bring the values incoming sales orders into account-based Profitability Analysis?
- A. A new standard G/L ledger with exclusive usage of "Prediction"
- B. An extension ledger of type "Simulation"
- C. An extension ledger of type "Prediction and Commitment"
- D. A multi-valuation ledger
Answer: C
NEW QUESTION 43
You are creating new activity type and want to maintain plan prices for a cost center. Which attribute must you configure in the activity type master record? Note: There are 3 correct answers to this question.
- A. Company code
- B. Activity type category
- C. CO version
- D. Price indicator
- E. Valid cost center categories
Answer: B,D,E
NEW QUESTION 44
To which object can you settle an internal order using cost elements with cost element category 21 (internal settlement)? Note: There are 3 correct answers to this question.
- A. Sales order item
- B. Network
- C. WBS element
- D. Asset
- E. General ledger account
Answer: A,B,C
NEW QUESTION 45
Which field can you select for both reporting in costing based and account-based Profitability Analysis?
- A. Version
- B. Value in Controlling Area Currency
- C. Record type
- D. Cost element
Answer: A
NEW QUESTION 46
In the material master record there are three planned prices: ""Planned price 1"", ""Planned price
2""and""Planned price 3"". What do you use them for?
- A. To update the standard price during the release of a standard cost estimate
- B. To valuate the materials in cost estimates
- C. To valuate material stocks
- D. To valuate goods movement
Answer: B
NEW QUESTION 47
Which of the following statements best describe Product Cost by Order? Note: There are 2 correct answers to this question.
- A. It is used when you perform repetitive manufacturing.
- B. It is used when controlling by individual production lots or discrete quantities is needed.
- C. It is recommended for products with a long production time.
- D. It is used when full cost traceability is needed.
Answer: B,D
NEW QUESTION 48
You want to create a new standard cost estimate based on the quantity structure of the existing standard cost estimate. Which object do you use?
- A. Transfer control
- B. Costing version
- C. Costing type
- D. Reference variant
Answer: A
NEW QUESTION 49
Which of the following objects can be selected in templates for activity-based costing? Note: There are 2 correct answers to this question.
- A. Cost center/activity type
- B. Internal order
- C. WBS element
- D. Business process
Answer: B,C
NEW QUESTION 50
How does the system derive the requirement type from the material master data? Note: There are 2 correct answers to this question.
- A. Strategy group -> planning strategy -> requirements type
- B. MRP group -> Strategy group -> planning strategy -> requirements type
- C. Strategy group -> planning strategy -> requirements class -> requirements type
- D. MRP group -> requirements class -> planning strategy -> requirements type
Answer: A,B
NEW QUESTION 51
How can you configure the transfer price solution in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Use separate CO versions for each valuation.
- B. Use separate ledgers for each valuation.
- C. Use separate segments for each valuation.
- D. Use separate currency types within the same ledger for each valuation.
Answer: A,B
NEW QUESTION 52
You want to create cost centers for your company. What is the prerequisite to build an organizational structure for overhead cost controlling?
- A. Person responsible
- B. Profit center
- C. Cost center categories
- D. Standard hierarchy top node
Answer: D
NEW QUESTION 53
Which statement best describes the Query Browser for reporting?
- A. It is the frontend used to define reports in Analysis for Office.
- B. It is available as an additional license product in SAP S/4HANA.
- C. It is a design studio app that comes as standard SAP Fiori content.
- D. It is a desktop browser that integrates with SAP S/4HANA.
Answer: D
NEW QUESTION 54
You want enable WIP calculation in Product Cost by Period. What do you need to configure?
- A. Profitability Analysis (PA) transfer structure
- B. Valuation variant
- C. Settlement profile
- D. Variance variant
Answer: B
NEW QUESTION 55
Which of the following statements apply to SAP S/4HANA embedded analytics? Note: There are 2 correct answers to this question.
- A. It is the core SAP S4/HANA license and users the same technical stack and user interface.
- B. It is hosted on the SAP Cloud Platform and integrate seamlessly on the SAP S4/HANA on the Fiori Launchpad.
- C. It uses core data services (CDS ) views to create virtual data models (VDMs ) for reporting.
- D. It is used by dedicated BI users who need to go beyond the capabilities of Strategic Analysis Tools for reporting.
Answer: A,C
NEW QUESTION 56
You are considering using commitment management with internal orders. What do you need to do in the configuration?
- A. Activate commitment management in the controlling area, the order type, and in individual internal order master data.
- B. Activate commitment management in both the version and the order type.
- C. Activate commitment management in both the controlling area and the order type.
- D. Activate commitment management only in the controlling area.
Answer: C
NEW QUESTION 57
In the Product Cost by Order process, what does the system calculate depending on the order status?
- A. WIP at target costs or variances
- B. WIP at percentage of completion (PoC) method or variances
- C. WIP at actual costs or variances
- D. Both WIP and variances
Answer: C
NEW QUESTION 58
What can you configure in the settlement profile? Note: There are 2 correct answers to this question.
- A. Define a number range for settlement document.
- B. Define document management parameters.
- C. Determine an overhead key.
- D. Determine whether settlement is required.
Answer: B,D
NEW QUESTION 59
In which module do you process profit center allocations in SAP S/4HANA?
- A. Product cost accounting
- B. Account-based profitability analysis
- C. Cost center accounting
- D. General ledger accounting
Answer: D
NEW QUESTION 60
Which default values can you configure for the product cost collector? Note: There are 2 correct answers to this question.
- A. Result Analysis (RA) Version
- B. Costing variant for preliminary costing
- C. Variance variant
- D. Result Analysis (RA) key
Answer: B,D
NEW QUESTION 61
You want to maintain a cost component structure. What can you determine for each cost component? Note:
There are 3 correct answers to this question.
- A. Relevance of cost component to inventory valuation
- B. Relevance of cost component to results analysis
- C. Assignment of cost component of cost component group
- D. Assignment of cost component to calculation base for overheads in costing sheet
- E. Relevance of cost component to goods manufactured
Answer: A,C,E
NEW QUESTION 62
You want to use budget availability control for your projects and internal orders. What can you check using budget availability control? Note: There are 2 correct answers to this question.
- A. The availability of funds on period level
- B. The availability of funds according to tolerance limits
- C. The availability of funds in object currency
- D. The availability of funds using overall plan value
Answer: B,C
NEW QUESTION 63
......
C_TS4CO_2021 Exam Certification Details:
| Cut Score: | 64% |
| Duration: | 180 mins |
| Languages: | German, English, French, Japanese, Chinese |
| Sample Questions: | SAP C_TS4CO_2021 Exam Sample Question |
Real Updated C_TS4CO_2021 Questions & Answers Pass Your Exam Easily: https://www.braindumpspass.com/SAP/C_TS4CO_2021-practice-exam-dumps.html
Easily To Pass New C_TS4CO_2021 Verified & Correct Answers: https://drive.google.com/open?id=10GFrCxBh0WgtRBKThclNAjRQPWPrt5CB