NEW QUESTION # 54
Which is a purpose of the Directing a Project process?

  • A. Delegate day-to-day management of the project to the Project Manager
  • B. Create and authorize the project mandate
  • C. Ensure that work on products allocated to the team is authorized and agreed
  • D. Control the day-to-day running of the project

Answer: A

Explanation:
Section: Volume A


NEW QUESTION # 55
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

  • A. Highlight Report
  • B. Checkpoint Report
  • C. Configuration Item Record
  • D. Quality Register

Answer: B

Explanation:
Section: Volume B


NEW QUESTION # 56
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

  • A. a temporary
  • B. a technical
  • C. a corporate
  • D. an external

Answer: A

Explanation:
Section: Volume A


NEW QUESTION # 57
Which is an objective of the Starting up a Project process?

  • A. Identify who will be responsible for creating the Project Plan
  • B. Agree how issues and changes will be identified, assessed and controlled
  • C. Agree how the project will be monitored and controlled after initiation
  • D. Authorize the Project Manager to proceed with the initiation stage

Answer: A


NEW QUESTION # 58
Which is NOT included in the PRINCE2 definition of a project?

  • A. A project is based on an agreed Business Case
  • B. A project is a temporary organization
  • C. A project'spurpose is to deliver one or more business products
  • D. A project is part of business as usual'

Answer: D


NEW QUESTION # 59
Which process is used by the project board to respond to on exception report?

  • A. Managing product delivery
  • B. Directing a project
  • C. Managing a stage boundary
  • D. Controlling a stage

Answer: B


NEW QUESTION # 60
Identify the missing word(s) in the following sentence.
The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

  • A. team plan
  • B. benefit
  • C. delivery stage
  • D. delivery step

Answer: C


NEW QUESTION # 61
Which is a minimum requirement for applying the quality theme?

  • A. The quality management approach must align with corporate standards
  • B. A record must be kept of all the quality management activities that are planned
  • C. The quality review technique must be used when reviewing products
  • D. Appraisal methods of quality control must be carried out on products

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:


NEW QUESTION # 62
Which is a responsibility of the project board?

  • A. To ensure production of the project's outputs
  • B. To ensure effective communication with external stakeholders
  • C. To manage the team managers and project support
  • D. To implement the change control approach

Answer: B


NEW QUESTION # 63
What is the collective name for individuals or groups who may be affected by a project?

  • A. Project Support
  • B. Team members
  • C. Customers
  • D. Stakeholders

Answer: D

Explanation:
In PRINCE2, the collective name for individuals or groups who may be affected by or can influence a project is "Stakeholders." This includes a wide range of people such as customers, users, team members, and suppliers, each of whom has an interest in the project's successful execution and outcomes. References:
PRINCE2 Foundation manual, PRINCE2 official resources


NEW QUESTION # 64
Which of the following statements about the Closing a Project process are true?
1.The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2.The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

  • A. Neither 1 or 2 are true
  • B. Only 2 is true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

Answer: B


NEW QUESTION # 65
The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.
In which step of the 'issue management technique should the change authority request this information?

  • A. Capturing issues
  • B. Assessing issues
  • C. Deciding on changes
  • D. Implementing changes

Answer: B

Explanation:
When the change authority asks for more information regarding a proposed change, this occurs during the
'Assessing issues' step of the 'issue management technique' in PRINCE2. This step involves evaluating the impact and implications of issues or changes, including requesting additional information necessary to make informed decisions.References: PRINCE2 7 Foundation resources on issue and change management.


NEW QUESTION # 66
Which is a purpose of the Quality theme?

  • A. Establish how the project will ensure that all products created meet their requirements
  • B. Establish quality assurance to maintain the quality management system
  • C. Identify all the products of the project to ensure the scope has been adequately defined
  • D. Determine the communication needs of the organization's quality assurance function

Answer: A


NEW QUESTION # 67
Within which integrated element does PRINCE2 set minimum requirements?

  • A. Principles
  • B. Processes
  • C. Themes
  • D. Project environment

Answer: C

Explanation:
Section: Volume B


NEW QUESTION # 68
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

  • A. Risk status
  • B. Risk response
  • C. Risk description
  • D. Risk category

Answer: B

Explanation:
Section: Volume B


NEW QUESTION # 69
Which is an objective of the Initiating a Project process?

  • A. Request authority from corporate management to deliver the project
  • B. Prepare the plans for the subsequent stages
  • C. Summarize how the organization's project management method will be tailored for the project
  • D. Develop the corporate quality management system as part of the Project Initiation Documentation

Answer: C

Explanation:
One of the key objectives of the Initiating a Project process is to tailor the organization's project management method to suit the specific requirements of the project. This involves adapting processes, controls, roles, responsibilities, and techniques to ensure they are appropriate for the project's context. References:
PRINCE2 Foundation official documentation and study materials.


NEW QUESTION # 70
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

  • A. Risk status
  • B. Risk response
  • C. Risk description
  • D. Risk category

Answer: B

Explanation:
Risk response refers to the actions identified and implemented to bring the risk exposure to an acceptable level. These actions are part of the risk management process and aim to reduce, avoid, transfer, or accept risks depending on their potential impact on the project. References: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


NEW QUESTION # 71
Which of the following describes a use of a Configuration Item Record?

  • A. To provide information on the approval procedure for the Work Package
  • B. To pass responsibility for the delivery of a product to a Team Manager
  • C. To record how changes to a product will be controlled
  • D. To record the history of a product

Answer: D


NEW QUESTION # 72
During the Initiating a Project process, which product is updated to incorporate the estimated time and costs from the Project Plan?

  • A. Project Brief
  • B. Project Product Description
  • C. Project mandate
  • D. Business Case

Answer: D


NEW QUESTION # 73
Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,

  • A. benefits, progress, risk,
  • B. benefits, customers, quality,
  • C. change, quality, progress,
  • D. benefits, quality, risk,

Answer: D


NEW QUESTION # 74
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

  • A. Off-specifications
  • B. Risk Register
  • C. Issue Register
  • D. Follow-on action recommendations

Answer: D

Explanation:
Follow-on action recommendations are used to document any uncompleted work or additional actions required after the project closure. These recommendations ensure that any outstanding issues or incomplete deliverables are addressed, even after the project has officially closed. References: PRINCE2 Foundation official study guide and materials.
These responses are crafted based on the official PRINCE2 guidelines and documentation, ensuring that they are reflective of the most current practices within the PRINCE2 methodology.


NEW QUESTION # 75
What needs to be in place to ensure effective issue and change control?

  • A. Manage by exception
  • B. Configuration management system
  • C. Quality planning
  • D. Information needs for stakeholders

Answer: B


NEW QUESTION # 76
......


PRINCE2 (PRojects IN Controlled Environments) is a widely recognized project management methodology that helps project managers to effectively deliver projects within the specified time, budget, and scope. The PRINCE2 framework is based on best practices and is widely used in both public and private sectors across the globe. PRINCE2 Foundation certification is the entry-level certification that provides a basic understanding of the PRINCE2 methodology.

 

PR2F Exam Practice Materials Collection: https://www.braindumpspass.com/EXIN/PR2F-practice-exam-dumps.html

Get Latest and 100% Accurate PR2F Exam Questions: https://drive.google.com/open?id=1a6XwXwxlhZbA0zeVVdHO70DYdWal1xvR