SAP C-TS412-1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.

 

NEW QUESTION 19
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

  • A. Structure information system reports
  • B. Cost element reports
  • C. Resource reports
  • D. Hierarchical reports

Answer: A

 

NEW QUESTION 20
Which object is used to allocate the costs from a claim to the project structure?

  • A. Internal order
  • B. Network activity
  • C. Claim
  • D. WBS element

Answer: A

 

NEW QUESTION 21
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?

  • A. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
  • B. Set up the requirement date manually as February 5.
  • C. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
  • D. Set up the requirement date aligned with the activity start date and an offset of 5 days.

Answer: D

 

NEW QUESTION 22
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.

  • A. Trigger automatic capacity leveling inside the project planning board.
  • B. Maintain subordinate internal activity elements assigned to other work centers.
  • C. Increase the capacities of the work center in the project planning board.
  • D. Shift activities backward or forward on the time axis where more capacities are available.

Answer: A,D

 

NEW QUESTION 23
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
  • B. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
  • C. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
  • D. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
    -> Purchase order monitoring -> Goods receipt -> Invoice receipt

Answer: A

 

NEW QUESTION 24
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Controlling area
  • B. Sales organization
  • C. Operating concern
  • D. Company code
  • E. Plant

Answer: A,D,E

 

NEW QUESTION 25
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.

  • A. Internally processed activities
  • B. Material components
  • C. Document information records
  • D. Basic dates for activities
  • E. Relationships

Answer: A,B,E

 

NEW QUESTION 26
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

  • A. Network profile
  • B. Project profile
  • C. Parameters for the network type
  • D. Network type

Answer: C

 

NEW QUESTION 27
What functionality can you perform with activity elements?

  • A. Assign work centers and capacities
  • B. Create relationships
  • C. Assign material
  • D. Schedule WBS elements

Answer: B

 

NEW QUESTION 28
Which report can use user-specific layouts?

  • A. Line item report
  • B. Enhanced individual overview
  • C. Cost element report
  • D. Hierarchical report

Answer: A

 

NEW QUESTION 29
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.

  • A. Released WBS elements, activities, and/or activity elements
  • B. A header-account-assigned network that is assigned to a sales order item
  • C. A dynamic item processor (DIP) profile with the appropriate settings
  • D. An activity-account-assigned network that is assigned to a sales order item

Answer: A,C

 

NEW QUESTION 30
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.

  • A. Background activation (CJBV - Activate Availability Control)
  • B. Automatic activation with the first actual posting
  • C. Automatic activation with assignment to an investment program
  • D. Automatic activation with budget assignment

Answer: A,D

 

NEW QUESTION 31
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  • A. Results analysis key
  • B. Investment profile
  • C. Costing sheet
  • D. Settlement rule

Answer: C

 

NEW QUESTION 32
You are working with networks and WBS elements. Which of the following statements applies?

  • A. You can assign the network header to multiple WBS elements.
  • B. You can reassign an activity from one network to another.
  • C. You have to maintain a network profile in the project profile.
  • D. You have to activate the operative indicator Account Assignment Element for WBS elements with activities.

Answer: A,B

 

NEW QUESTION 33
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

  • A. Basic dates of the WBS
  • B. Basic dates of the network activity
  • C. Actual dates of the network activity
  • D. Forecast dates of the WBS

Answer: B

 

NEW QUESTION 34
......